Worked scenario

A team of six sent to a site with no power

Wasted labour days in fit-out are almost always site-readiness failures, and the readiness check is the step most often skipped.

3 min read

A team arrives to install. The room is not plastered, or the power is not connected, or a preceding trade has not finished. The day is lost.

General confirmation is not confirmation

Asked whether the site is ready, a main contractor says yes, because from their position it is nearly ready. Specific conditions — power, floor finished, room clear — produce a different answer.

Record the wasted day

Absorbed silently, it looks like ordinary cost. Recorded against the project with its cause, it becomes either a claim or an argument for changing how deployment is confirmed.

Reassignment needs visibility

A team stood down on one site could sometimes work on another, but only if someone can see what else is ready today. That requires a view across sites rather than per project.

What changes

  • Readiness confirmed against specific conditions before deployment
  • Wasted days recorded against the project and the cause
  • Teams reassigned rather than stood down where possible
  • Contractors with recurring readiness failures identified